Lead times depend on order volume and customization, but in-house manufacturing removes many supply-chain bottlenecks. A typical AIDC project runs approximately 9 months from assessment to energization, with factory pre-integration and site work running in parallel.Short answer
Typical AIDC deployment schedule
Phase Typical duration Assessment & planning 4–6 weeks Factory pre-integration 11–15 weeks Logistics & site delivery 4–8 weeks On-site commissioning 5–7 weeks Upgrade & scaling Ongoing Why the schedule holds